Summary of installation tasks

Follow the steps in the following table to install your device. Details for each of these steps are provided on the pages indicated.

Installation tasks

Task number

Task

Where to find more information

1

Ensure that the physical environment that will host the device has the proper cabling and ventilation.

Preparing the installation site section

2

Unpack the device and all included accessories.

Items included with the ICX 7250-EPS 4000 section

3

Install the device on a desktop, or in an equipment rack.

Installing the device section

4

Once the device is installed, plug the device into a nearby power source that adheres to the regulatory requirements outlined in this manual.

Powering on the system section

5

Verify that the device is working properly by plugging it into a power source and verifying that it passes the self test.

Verifying proper operation section