Enabling Ekahau and Aeroscout/Stanley RTLS Tags
To locate tag positions, SmartZone allows
you to enable Ekahau and Aeroscout/Stanley RTLS tags.
- Select .
- Select a zone to enable the tags.
- To enable Ekahau Tag Support, set Ekahau Tag Support to ON.
- In the Server IP Address field, enter the IP address of the server to which data is forwarded.
- In the Server Port field, enter the server port to which data is forwarded.
- To enable Stanley Tag Support, set Stanley Tag Support to ON.
- Click OK.